Hammersmith W6

Refurbishment

Project durationProject sizeIndustryServicesClient
4 weeksResidential FlatPrivate propertyRefurbishmentPrivate
Project durationProject sizeIndustryServicesClient
4 weeksResidential FlatPrivate propertyRefurbishmentPrivate

Project scope

Ground and first floor internal refurbishment.

Following a list of client requirements and confirming a detailed scope of works with approved samples for all finishes a programme was issued outlining the durations and sequencing.

The project works consisted of the following:

  1. Strip out kitchen, strip out bathroom & strip out ground floor toilet
  2. Fit new ground floor WC where kitchen was located
  3. Fit client supplied kitchen in new location on ground floor area
  4. Fit new bathroom on 1st floor
  5. New decorations to ground floor kitchen, toilet and piano room
  6. New tiles floor to kitchen, bathroom toilet and reception room
  7. Install new drawer cupboard under staircase